Concrete Cost Calculator

Estimate ready-mix, labor, rebar, forms, and finish for a rectangular pour. Enter dimensions once — you get a low / typical / high range, not a single number that pretends to be a bid.

Project dimensions

Add-ons

Estimated installed cost

$987$2,749

Typical ~$1,868 · $5$14/sq ft

Volume (raw)
2.47 cy
With waste
2.59 cy
Area
200 sq ft

Short load: under 4 cy — plants often add a $50150 surcharge.

Cost breakdown

  • Ready-mix concrete (delivered)2.59 cy × $130–$200/cy$337$519
  • Short-load surchargeOrder under 4 cy$50$150
  • Labor — place & finish200 sq ft × $2.50–$8.00/sq ft$500$1,600
  • Rebar / wire mesh200 sq ft × $0.20–$1.50/sq ft$40$300
  • Formwork60 lf perimeter × $1.00–$3.00/lf$60$180

Not included

  • Excavation and grading
  • Base gravel / compacted subbase
  • Removal of existing concrete
  • Permits and inspections
  • Difficult site access or pumping beyond a standard day rate

Price data updated . National US ranges from published supplier and contractor averages. Not a bid. Local quotes vary.

How this concrete cost calculator works

Volume comes first. For a rectangular slab:

cubic feet  = length (ft) × width (ft) × (thickness (in) ÷ 12)
cubic yards = cubic feet ÷ 27
order yards = cubic yards × (1 + waste %)

Worked example. A 20 × 20 ft × 4 in slab is about 4.94 cy before waste. At national ready-mix and labor bands, installed totals typically land in the low thousands depending on rebar, forms, and finish — use the calculator for the live range.

Concrete cost components (US national ranges)

Line items this calculator uses. Regional quotes move with cement, fuel, and crew availability.

ComponentTypical range
Ready-mix delivered$130–$200 / cy
Short-load surcharge$50–$150 under ~4 cy
Place & finish labor$2.50–$8.00 / sq ft
Rebar / mesh$0.20–$1.50 / sq ft
Forms$1–$3 / lf perimeter
Pump truck$600–$1,200 / day
Stamped finish uplift$8–$18 / sq ft

Concrete Cost calculator FAQ

Does this concrete cost calculator include labor?
Yes. The total includes ready-mix delivery plus a place-and-finish labor range ($2.50–$8.00 per sq ft). Optional line items cover rebar, forms, pump truck, and stamped finish. Excavation, base gravel, demo, and permits are listed separately as exclusions.
How much extra concrete should I order?
Most residential pours add 5–10% for waste and uneven subgrade. This calculator defaults to 5%. Complex shapes, thick edges, or inexperienced crews may need closer to 10%. Ordering short and needing a second truck is usually more expensive than a small leftover.
What is a short-load surcharge?
Ready-mix plants often charge an extra $50–$150 when the order is under about 4 cubic yards because the truck and plant still incur nearly the same fixed cost. If your volume is small, compare bagged concrete — see the bag calculator — or combine pours on one delivery day.
How thick should a concrete driveway or patio be?
A typical residential driveway slab is 4 inches thick over compacted base; heavy vehicles or poor soil may call for 5–6 inches and heavier reinforcement. Patios and walkways are often 4 inches. Always follow local code and your engineer or inspector when required.
Is this a concrete price calculator or a contractor quote?
It is a planning estimate using national US price ranges. Local ready-mix, labor markets, access, and finish quality move the number. Use the low/typical/high range to budget and to compare bids — not as a fixed price.
Why do stamped finishes cost so much more?
Stamped and decorative work adds color hardener, release agents, stamping labor, and often sealing. This tool adds an $8–$18 per sq ft uplift on top of standard place-and-finish labor. Intricate patterns and multi-color jobs sit at the high end.